Takreer / Tecnimont Heaters

Takreer / Tecnimont Heaters

Takreer / Tecnimont Heaters

Client: Takreer/Tecnimont
Execution Period: 2010 – 2011
Services: Refurbishment

Project Description:
Pre-fabrication of components for convection and radiant section of two condensate heaters incl. inspection and overhaul of burners
Supply and replacement of skin thermo-couples, refractory and insulation
All site works to be completed within a shut down duration of 35 days for each heater

Plant Description:
Heaters for the condensate trains (2 x140,000 BPD)

  • Takreer / Tecnimont Heaters