EMAL Power Plant BOP

EMAL Power Plant BOP

EMAL Power Plant BOP

Client: Emirates Aluminum
Location: Taweelah, Abu Dhabi
Execution Period: 2009 – 2010
Services: Construction & BOP

Project Description:
Construction of 2000 MW power complex at the aluminum smelter Erection of 4 HRSGs and BOP equipment and piping for 6 gas turbines and 2 steam turbines including welding, NDT, hydro testing, refractory and insulation works and commissioning support
Erection of sea water intake equipment and associated pipe work, including pre-commissioning

Plant Description:
Aluminum smelter with 2000 MW power plant

  • EMAL Power Plant BOP